August, 2011
NATIONAL ENERGY RESEARCH COMPUTING CENTER (NERSC)
|

A DOE and Lawrence Berkeley National Laboratory project in Oakland. 3 MW upgrade; two chiller plants; infrastructure support of the 5th fastest Super Computer (Hopper). 24/7 facility remained in operation during construction.
more...
|

|
June 11, 2011
UCSC THIN FILMS and MATERIAL LABORATORY, SANTA CRUZ
|
NEW RESEARCH LABORATORY.
H-5 Occupancy. Highly combustible gases.2 hr separations. Area: 10,000 sq. ft.
more...
|

|
January, 2011
NATIONAL IGNITIAN LABORATORY (NIF),
LAWRENCE LIVERMORE NATIONAL LABORATORY
|
INSTALLATION OF DIAGNOSTIC COLLIMATORS WITHIN THE TARGET BAY. Associated improvements. Tight tolerances within a six ft. concrete shield surrounding the target bay. Facility is engaged in fusion research.
more...
|

|
August, 2010
MILLS COLLEGE FOUNDERS HALL, OAKLAND
|
RENOVATION OF FOUNDER'S HALL STUDENT DINING FACILITY. New cook line, food service equipment, boilers, finishes, lighting, deferred maintenance.
more...
|

|
July, 2010
PHILIPS LUMILEDS AMMONIA PLANT, SAN JOSE
|
PLANT EXPANSION FOR BULK AMMONIA RECEIVING AND STORAGE FACILITY. All work took place during full 24/7 occupancy.
more...
|

|
June, 2010
MORGAN HALL LABORATORY,
UC BERKELEY
|
LEED LABORATORY RENOVATION. INCLUDED FIRE SUPRESSION; SHAFT FOUR FLOORS TO THE ROOF.
Area: 4,000 sq. ft. First LEED laboratory project in the UC System.
more...

|

|
May, 2010
TOKYO ELECTRON,
FREMONT
|
RELOCATION OF AN ELECTRONICS FACILITY FOR THE MANUFACTURE OF WAFER CALIBRATION INSTRUMENTS.
Area: 60,000 sq. ft. with a 6,100 sq. ft. clean room and strict atmospheric controls. Design assist. Including cost options for alternative properties.
more...
|
| |
|

3 Weeks Earlier

|
UC BERKELEY – BOALT SCHOOL OF LAW
INTERIOR RENOVATION PROJECT

University of California, Berkeley, Boalt School of Law
A phased demolition and renovation of classrooms, meeting rooms, student areas and offices while building was fully occupied. James R, Griffin, Inc. crews worked nights and weekends in order to successfully meet class room schedules and demanding deadlines. The project included new lecture halls with state of the art distant learning capabilities and production studios. New work included a variable refrigerant HVAC system, new electrical and data systems, and sophisticated AV technology. A LEED certified project.
Cost: $15,000,000.
|
|
|
|
|

5th Straight Year
2006, 2007, 2008, 2009, 2010
|

Our employees are proud of our company’s safety record. All eyes are set to ensure safe conditions.
|
|
|
|
|

|

|
|
|


********* AWARDS **********
* 2009 California Restoration Award in the Larger Projects Category
* Society for College and University Planning
(SCUP) Award
* Building America Award
for "one of the "most imaginative, unique and immaculate projects in the North West", by Real Estate & Construction Review |
Mills College Concert Hall, Oakland

HISTORIC CONCERT HALL, MILLS COLLEGE, OAKLAND,
Originally designed by Walter Ratcliff, Jr. and built in 1928, James R. Griffin, Inc. was entrusted to perform major seismic reconstruction work, including new foundations and concrete sheer walls. In the concert hall the old floor framing and walls were demolished and new, reconfigured floors and seating installed.
New undulating walls were constructed to improve acoustics and enhance the beauty of the room. A new roof with seismic connections and acoustic improvements was installed, along with new heating and electric systems, new office and bathroom wing and a new elevator. All concrete and framing operations were conducted by the crews of James R, Griffin, Inc. The project was completed on time and under budget. Cost: $8,000,000.
|
|
|
|


This many trucks in 1 day!
|
VARIAN MEDICL SYSTEMS, PALO ALTO
TEST CELLS AND PHASED MANUFACTURING LINE RENOVATION

| Six radiation test cells for linear accelerators used in the treatment of cancer, each with five foot thick concrete walls and ceilings; phased 20,000 sq. ft. manufacturing assembly line without interrupting facilities operations. James R. Griffin, Inc. completed the project five weeks ahead of schedule. Project included upgrading the entire electrical infrastructure for the plant. Total cost: $13,750,000. |
|
|
|


|
BETTY IRENE MOORE NATURAL SCIENCES BUILDING
MILLS COLLEGE, OAKLAND

James R. Griffin, Inc. was selected as a member of a multi discipline team to design and build a 26,000 sq. ft. addition to the Sciences Buildings complex in the heart of the Mills College campus in Oakland with the goal of achieving LEED Gold certification.
Working closely with the campus architect, our company was active in finding ways to raise the certification to LEED PLATINUM LEVEL while remaining on budget and on schedule. Included in the project were significant modifications within the 46,000 sq. ft. multi building complex. Cost: $13,800,000. |
|
|
|


|
Pacific Heights San Francisco Apartment Renovation Project
Published in Architectural Digest

|